Study 1 - Feasibility Study (Optional)

An optional Feasibility Study examines whether the interconnection will be possible. It includes power flow and short circuit analyses as well as a high-level estimate of cost responsibility and a non-binding, good-faith estimate of time to construct.

WHAT YOU DO

  • Execute the Feasibility Study Agreement (Appendix 2) of the LGIP
  • Submit a $10,000 deposit to TEP
  • Submit all required technical data to interconnect your project

WHAT TEP DOES

  • Provides you with an Interconnection Feasibility Study Agreement (Appendix 2)
  • Completes the Feasibility Study within 45 calendar days and provides the report to you
  • Holds a Feasibility Study Review meeting with you once the study is completed